Rm-materials-handling WIRE ROPE HOISTS Service Bedienungsanleitung Seite 112

  • Herunterladen
  • Zu meinen Handbüchern hinzufügen
  • Drucken
  • Seite
    / 130
  • Inhaltsverzeichnis
  • FEHLERBEHEBUNG
  • LESEZEICHEN
  • Bewertet. / 5. Basierend auf Kundenbewertungen
Seitenansicht 111
R&M Materials Handling, Inc.
4501 Gateway Boulevard
Springfield, Ohio 45502
P.: (937) 328-5100
FAX: (937) 325-5319
112/130
R&M Materials Handling, Inc. reserves the right to alter or amend the above information without notice.
Adjust the side plate (5) of the trolley inwards by turning the screws (3) until there is a gap of
approximately 3…5mm between the flange of the travel wheels and the flange of the beam.
Adjust the position of the trolley so that the hook is hanging below the centerline of the beam. Lock
the position by tighten the nuts (2).
! Tighten the nuts (2) and the screws (4) to the correct tightening torque. Refer to the section
'Recommended tightening torques'.
6.5.3 Outfitting the hoist
Install the power supply. Refer to the section “Connecting the to mains network”.
Adjust the limit switch for hoisting. Refer to the section “Adjusting hoisting limit switch”.
Carry out the commissioning inspection and complete the commissioning log. Refer to the section
“Commissioning”.